The first shipment for one of India’s leading steelmaker’s new Continuous Galvanizing Line (CGL) and flexible steel processing line, combining continuous galvanizing and annealing (CGAL), left our workshop close to 2 months ahead of schedule. What a great recognition for all members of our passionate project team who helped us hit this important milestone.
With the completion of the Basic Design at the end of August 2022, the first project milestone was already reached within the agreed time schedule. The first dispatch to the client’s site in the state of Gujarat, is the second important milestone of John Cockerill Industry’s biggest order ever and the first of many more to come in the months ahead. Upon its completion, the overall volume of the equipment deliveries will amount to around 20,000 tons.
John Cockerill is proud to accompany its steelmaking client in the production of sustainable high-performance steel.